Toronto building permit review time calculator
Choose the type of project and the date a complete application is taken in. The calculator counts the City of Toronto's published review time in weekdays and shows the last day of that window.
Last checked 2026-11-08 against the City of Toronto page on building permit review streams. The City does not define a business day or say when the clock starts for the non-Express streams, so this tool counts Monday to Friday starting the weekday after the date you enter and does not subtract statutory holidays. It shows the published review window only, not when work can start. General information, not professional advice.
We prepare the drawings and manage the permit
Our design team prepares the drawings, handles the application and any City comments, and builds the project, with one point of contact from start to finish.
Frequently asked questions
How long does Toronto take to review a building permit application?
Toronto Building publishes review times by stream. Complete applications in the House Stream are reviewed within 10 business days, in the Small Building Stream within 15 business days, and in the Large and Complex Building Stream within 20 business days for large buildings and 30 business days for complex buildings. Source: City of Toronto, Building permit review streams.
Which stream is my house or garden suite in?
The City says the House Stream includes a detached house, semi-detached house or row house containing not more than two dwelling units, and also ancillary buildings such as garden suites and laneway suites. The Small Building Stream includes buildings within the scope of Part 9 of the Building Code, excluding houses, and the Large and Complex Building Stream includes buildings within the scope of Part 3. Source: City of Toronto, Building permit review streams.
What counts as a complete application?
The City says the review timeframes apply only to complete applications, and that completeness requires, among other things, an issued Zoning Applicable Law Certificate and payment of all fees. An application without one is considered incomplete and has no review timeframe. Source: City of Toronto, Building permit review streams.
What is Express Services?
Express Services is an enhanced building permit service for certain types of projects: Small Residential, Small Commercial, Solar Panels and Sign Permits. Toronto Building's goal is to review eligible applications within 3 business days after the permit has been taken in. Source: City of Toronto, Building permit review streams.
Does this tell me when my permit will be issued?
No. It shows the last day of the City's published review time for a complete application, counting weekdays only. The City does not define a business day, does not say when the clock starts for the non-Express streams and does not mention holidays, so this tool does not subtract statutory holidays. The review time is also only one stage: drawings, zoning review, any corrections and the inspections that follow are separate.